1.【单选题】

The IT service manager has learned that a software canimprove the efficiency of current and future project tasks. Because the software is fresh to the Company. The engineer is not familiar with the software. The IT servicemanager decides to send the highest level engineer to attend the external training course. The project manageruses () risk strategies

A
mitigation
B
enhancement
C
development
D
sharing