1.In the project management context, ( ) includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.
A.integration
B.scope
C.process
D.charter
【答案】A
【解析】
在项目管理环境中,()包括统一.整合.表达和综合行动的特征,这些特征对项目完成.成功满足客户和其他利益相关者的需求以及管理期望至关重要。
A. 整合
B. 范围
C. 过程
D. 章程
2.On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and ( ) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
A.time estimating
B.cost estimating
C.project planning
D.schedule development
【答案】D
【解析】
在一些项目中,尤其是较小范围的项目,活动排序.活动资源估算.活动持续时间估算和()紧密地联系在一起,因此它们被视为一个单独的过程,可以由一个人在相对较短的时间内执行。
A. 时间估计
B. 成本估算
C. 项目规划
D. 进度计划制定
3.In approximating costs, the estimator considers the possible causes of variation of the cost estimates, including( ) 。
A.budget
B.plan
C.risk
D.contract
【答案】C
【解析】
在估计成本时,估计者考虑了成本估计变化的可能原因,包括( )
A. 预算
B. 计划
C. 风险
D. 合同
距离2020年软考高级职称准考证打印还有一段时间,考生可提前 免费预约短信提醒服务,届时会提示您2020年软考高级职称准考证打印时间.考试时间,让您安心备考。
以上内容为2020年软考高级信息系统项目管理师考试英语练习题三,小编为广大考生上传更多2020年软考高级职称考试历年真题.模拟试题等供大家学习,如有需要请点击文章下方“免费下载”获取相关内容。
最新资讯
- 软考高级题库「信息系统项目管理师」每日5题(11月8日)2024-11-08
- 软考高级题库「信息系统项目管理师」每日5题(11月7日)2024-11-07
- 软考高级题库「信息系统项目管理师」每日5题(11月6日)2024-11-06
- 软考高级题库「信息系统项目管理师」每日5题(11月5日)2024-11-05
- 软考高级题库「信息系统项目管理师」每日5题(11月2日)2024-11-04
- 软考高级题库「信息系统项目管理师」每日5题(11月1日)2024-11-01
- 考高级题库「信息系统项目管理师」每日5题(10月31日)2024-10-31
- 软考高级题库「信息系统项目管理师」每日5题(10月29日)2024-10-29
- 软考高级题库「信息系统项目管理师」每日5题(10月28日)2024-10-28
- 软考高级题库「信息系统项目管理师」每日5题(10月25日)2024-10-25