2020年软考高级信息系统项目管理师考试英语练习题十四
1. An example of scope verification is __.
A.review the performance ofan installed software module
B.managing changes to the projectschedule
C.decomposing the WBS to a workpackage level
D.performing a benefit/cost analysis to determineif we shuould proceed with the project
【答案】A
【解析】
范围验证的一个示例是__。
A.查看己安装的软件模块的性能
B.项目进度变更管理
C.分解到工作包级别WBS
D.执行成本/效益分析,以确定是否我们应该继续进行项目
范围验证,这一过程用于正式验收项目的阶段成果或项目的最终成果,也叫范围确认。验收的作用就是检查系统或软件是否能正常运行,所以选择A
2.Your project is behind schedule due toconflict between team members . Having resolved the conflict,to get the projectback on schedule , you should consider __.
A.crashing the schedule
B.performing resource leveling
C.conducting reverse resourceallocation scheduling
D.utilizing the critical chairresources
【答案】B
【解析】
由于团队成员之间的冲突,造成了项目进度落后于计划,为了解决冲突以使得项目如期完成,你应该考虑:A.重新安排时间表 B.执行资源调配 C.进行反向资源分配调度 D.利用关键的主要资源
3. The connection between two networks tofrom an internet is handled by a machine known as a __.
A.bridge
B.server
C.router
D.switch
【答案】C
【解析】
两个网络之间的连接是由一台名为“ ”的机器来处理的。
A. 桥梁
B. 服务器
C. 路由器
D. 开关
距离2020年软考高级职称准考证打印还有一段时间,考生可提前 免费预约短信提醒服务,届时会提示您2020年软考高级职称准考证打印时间.考试时间,让您安心备考。
以上内容为2020年软考高级信息系统项目管理师考试英语练习题十四,小编为广大考生上传更多2020年软考高级职称考试历年真题、模拟试题等供大家学习,如有需要请点击文章下方“免费下载”获取相关内容。
最新资讯
- 软考高级题库「信息系统项目管理师」每日5题(12月20日)2024-12-20
- 软考高级题库「信息系统项目管理师」每日5题(12月19日)2024-12-19
- 备考干货:软考高项经典计算题跟练(5)2024-12-17
- 备考干货:软考高项经典计算题跟练(4)2024-12-16
- 备考干货:软考高项经典计算题跟练(3)2024-12-13
- 备考干货:软考高项经典计算题跟练(2)2024-12-12
- 软考高级题库「信息系统项目管理师」每日5题(12月11日)2024-12-11
- 软考高级题库「信息系统项目管理师」每日5题(12月10日)2024-12-10
- 软考高级题库「信息系统项目管理师」每日5题(12月9日)2024-12-09
- 软考高级题库「信息系统项目管理师」每日5题(12月6日)2024-12-06