2020年软考高级信息系统项目管理师考试英语练习题七
1.During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised ( )are necessary.
A. proceedings
B. controls
C. forecasting’s
D. prelibations
【答案】B
【解析】
在项目过程中,由于各种原因,需求会发生变化。随着需求的变化和工作的进行,会产生额外的需求,可能需要对现有需求进行更改。必须有效地管理这些添加和更改。为了有效地分析变更的影响,有必要知道每个需求的来源,并记录任何变更的理由。然而,项目经理可能希望跟踪需求波动性的适当度量,以判断是否需要新的或修订的控制。
2.Project Quality Management processes include all the activities of the ( ) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.
A. project
B. project management team
C. performing organization
D. customer
【答案】C
【解析】
项目质量管理过程包括执行组织确定质量方针.目标和责任的所有活动,以使项目满足其所承担的需求。
3.The Estimate Activity Resource process is closely coordinated with the ( )process.
A. Estimate Costs
B. Sequence Activities
C. Plan Communications
D. Conduct Procurements
【答案】A
【解析】
估算活动资源过程密切协调使用()进程。
A. 估计费用
B. 序列活动
C. 计划沟通
D. 进行采购
距离2020年软考高级职称准考证打印还有一段时间,考生可提前 免费预约短信提醒服务,届时会提示您2020年软考高级职称准考证打印时间.考试时间,让您安心备考。
以上内容为2020年软考高级信息系统项目管理师考试英语练习题七,小编为广大考生上传更多2020年软考高级职称考试历年真题.模拟试题等供大家学习,如有需要请点击文章下方“免费下载”获取相关内容。
最新资讯
- 软考高级题库「信息系统项目管理师」每日5题(12月20日)2024-12-20
- 软考高级题库「信息系统项目管理师」每日5题(12月19日)2024-12-19
- 备考干货:软考高项经典计算题跟练(5)2024-12-17
- 备考干货:软考高项经典计算题跟练(4)2024-12-16
- 备考干货:软考高项经典计算题跟练(3)2024-12-13
- 备考干货:软考高项经典计算题跟练(2)2024-12-12
- 软考高级题库「信息系统项目管理师」每日5题(12月11日)2024-12-11
- 软考高级题库「信息系统项目管理师」每日5题(12月10日)2024-12-10
- 软考高级题库「信息系统项目管理师」每日5题(12月9日)2024-12-09
- 软考高级题库「信息系统项目管理师」每日5题(12月6日)2024-12-06