1.You have just taken control of aproject in the middle of execution and need to learn who has approval authorityfor revisions in scope . __ document provides this information.
A.Resource assignment matrix
B.Change control plan
C.Project charter
D.Client organization chart
【答案】B
【解析】
在项目执行的过程中你刚刚获得项目的控制权力,并且需要了解谁具有范围修正的权限,__文件提供了该信息?
A.资源分配矩阵B.变更控制计划 C.项目章程 D.客户的组织结构图
2.Quality planning tools are often used to help plan effective quality management activities.( ) is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.
A.Benchmarking
B.Quality metric
C.Quality checklist
D.Brainstorming
【答案】A
【解析】
质量计划工具通常用于帮助计划有效的质量管理活动。()是此类工具之一,它涉及到公司实际或计划的项目实践,以这些或其他项目产生改进的想法,并提供衡量绩效的依据。
A. 基准测试
B. 质量度量
C. 质量检查表
D. 头脑风暴
3.Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria.____is not a project selection method.
A.Benefit contribution
B.Expert judgment
C.Scoring models
D.Flow charting
【答案】D
【解析】项目选择方法包括测量项目业主或赞助人的价值或吸引力,并可能包括其他组织决策,标准流程图表不是项目选择方法。
距离2020年软考高级职称准考证打印还有一段时间,考生可提前 免费预约短信提醒服务,届时会提示您2020年软考高级职称准考证打印时间.考试时间,让您安心备考。
以上内容为2020年软考高级信息系统项目管理师考试英语练习题十三,小编为广大考生上传更多2020年软考高级职称考试历年真题、模拟试题等供大家学习,如有需要请点击文章下方“免费下载”获取相关内容。
最新资讯
- 软考高级题库「信息系统项目管理师」每日5题(11月21日)2024-11-21
- 软考高级题库「信息系统项目管理师」每日5题(11月20日)2024-11-20
- 软考高级题库「信息系统项目管理师」每日5题(11月19日)2024-11-19
- 软考高级题库「信息系统项目管理师」每日5题(11月15日)2024-11-15
- 软考高级题库「信息系统项目管理师」每日5题(11月11日)2024-11-11
- 软考高级题库「信息系统项目管理师」每日5题(11月8日)2024-11-08
- 软考高级题库「信息系统项目管理师」每日5题(11月7日)2024-11-07
- 软考高级题库「信息系统项目管理师」每日5题(11月6日)2024-11-06
- 软考高级题库「信息系统项目管理师」每日5题(11月5日)2024-11-05
- 软考高级题库「信息系统项目管理师」每日5题(11月2日)2024-11-04